In one of the E-LAND pilot sites (Auroville), the peak demand pricing scheme applies, but has an exception: The per-peak-demand price of a month is only used, when the peak demand of a month is larger than 90% of the sanctioned load. Currently, this can not be simulated (easily). But it would be easy to implement.
This way, only the OPTIMAL_ADD_CAP is connected to costs.
In one of the E-LAND pilot sites (Auroville), the peak demand pricing scheme applies, but has an exception: The per-peak-demand price of a month is only used, when the peak demand of a month is larger than 90% of the sanctioned load. Currently, this can not be simulated (easily). But it would be easy to implement.
sanctioned_loadtoenergyProviders.csvsanctioned_load, inmulti-vector-simulator/src/multi_vector_simulator/C0_data_processing.py
Line 993 in 5b5b79c
multi-vector-simulator/src/multi_vector_simulator/C0_data_processing.py
Line 718 in 5b5b79c
This way, only the
OPTIMAL_ADD_CAPis connected to costs.